1)As per the Advance Ruling Tanakpur power station, NHPC has been exempted from GST as per notification no. 12/2017,central tax(Rate) dated 28-06-17 (as amended time to time) but will this entails other agencies and contractor/ sub-contractors not to charge GST in their invoices. If the activity of constructing Indo-Nepal border rode is exempted as per advance ruling will this permit all the contractor and sub-contractors involved in this project be exempted or otherwise?
States/UT
Order No. & Date
Ruling No.17 dated 30.01.2019
Order date
30-01-19
Upload file
Category
97(2)(a)